On 28 January 2003, the Management
Objectives committee report was presented to the Water Conservation Alliance
(WCA). That report listed the top
priorities the WCA should consider in developing a new release protocol for the
Leesville Dam and the Smith Mountain Lake Project. As an outcome of this report the Protocol Committee was
established to study and develop a new release protocol. This purpose of this report is to detail the
efforts of the protocol committee and to report its findings.
J. Johnson Eller, esq. – Chairman,
Altavista, VA
William Brush – member, Smith
Mountain Lake, Bedford County, VA
J.T. Davis – member, Friends of
the Staunton River, Brookneal, VA
John Lindsey – member, Smith
Mountain Lake, Pittsylvania County, VA
Shelton Miles – member, Citizens
for Preservation of the River, Long Island, VA
William Reidenbach – member, Smith
Mountain Lake, Franklin County, VA
Teresa Rodgers – member, Reservoir
Manager, American Electric Power (AEP)
The committee attempted to
establish a protocol for releases that would fairly support all stakeholders
needs both above the Leesville Dam (upstream) to below (downstream) the
principal idea being to “share the pain” equitably in times of prolonged low
inflows. In formulating the protocol
principal priorities were:
During the course of four
meetings, the committee examined several release protocols and studied their
impact upon stream flow below the Leesville dam and on the water levels of
Smith Mountain Lake. Rather than
speculate on potential inflows into the project, the committee utilized
historical stream flow data from the United States Geological Survey (USGS),
evaporation rates from the Army Corps of Engineers and actual operational data
(1998 – 2002) from AEP.
A volumetric analysis was
developed in Microsoft Excel that utilized historical inflows to Smith Mountain
and Leesville Lakes, postulated possible release protocols from Leesville dam,
and projected stream flow for each release protocols at the downstream points
of Altavista, Brookneal and Randolph, VA.
Although several protocols were
studied, the committee focused upon three:
The committee was unable to reach
an agreement and recommend a specific protocol. However, several key points of agreement were reached, and these
key points should be utilized by the WCA as it continues its work.
The Protocol Committee recommends
that any release protocol incorporate the following key points:
1. The
current 650cfs protocol is not optimal during times of prolonged low inflows
because it results in very low lake levels.
2. The
ability of the system operator to generate electrical power must not be
compromised.
3. The
seasonal nature of stream flow and precipitation must be accommodated.
4. Minimum
release rates from Leesville must be sufficient to:
a. Ensure
adequate flow to meet downstream Municipal and Industrial water needs;
b. Ensure
adequate flow to meet DEQ minimum flow by at Altavista to assimilate sewage
effluent discharge and to preclude stagnation;
c. To
maintain the temperature and dissolved oxygen levels in the Staunton River
within the DGIF stated acceptable parameters to ensure the quality of the
water and to protect the fishery and the aquatic life of the river;
5. Minimum
release rates from 15 October through 31 March should not fall below 350cfs.
6. Minimum
release rates from 31 May through 15 October should not fall below 400cfs.
7. Between
February and March the project should “super charge” to 795.3 feet adjusted, to
support striper spawn releases
8. During
striper spawn, a 30 day period from April through May, release rates should
support an 1150cfs flow-by at Brookneal
9. The
release regimen must consider: public water withdrawals, rainfall, evaporation
rates, stream flow, lake levels, and downstream flow requirements at Altavista
and at Brookneal.
10. Upstream
and downstream recreational expectations must be fairly balanced.
The following map of the Roanoke
River Basin highlights the major inflows (blue arrows) into the Smith Mountain
Project and flow-by requirements (red arrows) at downstream points. The required flow-by at Altavista is 720cfs;
except under variance conditions, the flow-by can be reduced to as little as
360cfs. During striper spawn, the
flow-by requirement at Brookneal is 1150cfs.
The volumetric model was developed in Microsoft Excel and utilizes measured historical inflows from the Roanoke River, Blackwater River and Pigg River into Smith Mountain and Leesville Lakes. Release rates from Leesville Dam are varied in accordance with the protocol design. The Excel spreadsheet calculates the impact of the release protocol upon lake levels and downstream flow-by requirements at Altavista, Brookneal and Randolph, VA. Using this methodology, the committee was able to evaluate the performance of each proposed protocol under identical conditions. The simple volumetric model is shown below.
Basic Volumetric Model

The committee studied three release protocols:
1. The
Shelton Miles Release Protocol, initially suggested in his white paper to the
WCA on 29 April 2002;
2. The
Graduated Step Release Protocol, developed during this committee’s
deliberations;
3. The 650cfs
protocol currently required by the FERC for operation of the Smith Mountain
lake Project.
The charts below summarize the performance of each protocol under likely or expected drought conditions. The following charts are based on assumptions and extrapolations as well as hard data and while they were refined many times as a result of committee discussions the published versions are not the product of unanimous agreement.

Shelton Miles
Protocol Release Rates And Flow By At Downstream Gauges

Graduated Step
Protocol Release Rates And Flow By At Downstream Gauges

650 CFS Protocol Release Rates And Flow By At Downstream Gauges

Protocol
Performance Relative To Adjusted Lake Level
Actual Conditions 1998 to 2002
The following charts summarize the performance of each protocol under the actual conditions experienced between September 1998 and September 2002. The following charts are based on assumptions and extrapolations as well as hard data and while they were refined many times as a result of committee discussions the published versions are not the product of unanimous agreement.

Flow Performance 9/98 – 9/02 Shelton Miles Protocol

Flow
Performance 9/98 – 9/02 Graduated Step Protocol


Several key points of agreement were
reached, and these key points should be utilized by the WCA as it continues its
work. The Protocol Committee recommends
that any release protocol incorporate the following key points:
1. The
current 650cfs protocol is not optimal during times of prolonged low inflows
because it results in very low lake levels.
2. The
ability of the system operator to generate electrical power must not be
compromised.
3. The
seasonal nature of stream flow and precipitation must be accommodated.
4. Minimum
release rates from Leesville must be sufficient to:
a. Ensure
adequate flow to meet downstream Municipal and Industrial water needs;
b. Ensure
adequate flow to meet DEQ minimum flow by at Altavista to assimilate sewage
effluent discharge and to preclude stagnation;
c. To
maintain the temperature and dissolved oxygen levels in the Staunton River
within the DGIF stated acceptable parameters to ensure the quality of the
water and to protect the fishery and the aquatic life of the river;
5. Minimum
release rates from 15 October through 31 March should not fall below 350cfs.
6. Minimum
release rates from 31 May through 15 October should not fall below 400cfs.
7. Between
February and March the project should “super charge” to 795.3 feet adjusted, to
support striper spawn releases
8. During
striper spawn, a 30 day period from April through May, release rates should
support an 1150cfs flow-by at Brookneal
9. The
release regimen must consider: public water withdrawals, rainfall, evaporation
rates, stream flow, lake levels, and downstream flow requirements at Altavista
and at Brookneal.
10. Upstream
and downstream recreational expectations must be fairly balanced.
The committee was unable to reach
agreement and recommend a specific protocol.
Those specific areas of disagreement follow:
·
The specific events which would trigger reduced release
rates
·
The specific trigger level which would result in reduced
release rates
The essence of both the Shelton
Miles and Graduated Step Protocols is to conserve the water resource, as much
as is reasonably possible, during extended periods of low inflows, to enable
the Smith Mountain Project to better support all stakeholders in accordance
with the following priorities:
1. Upstream
and downstream public water withdrawals and sewage effluent dispersion;
2. Power
generation capability;
3. State
agency requirements including: water quality, sustenance of aquatic life, and
Striper and other fish species spawns;
4. Downstream
and upstream economic, recreational and tourism needs and expectations.
Key differences between the Shelton
Miles and the Graduated Step Protocols:
·
The Graduated Release triggers earlier on prolonged low
inflows and project levels and reduces the release rate in two steps: (1)
650cfs to 500cfs and (2) 500cfs to 400cfs, whereas the Shelton Miles protocol
delays the variance until the lake levels reach a lower level and then reduces
the release rate to 400cfs.
·
The Graduated Release recognizes lake navigation and public
safety issues when actual lake level falls below 792' and seeks to raise lake
levels to return to safe levels faster, whereas the Shelton Miles protocol
maintains higher flows in the Staunton River for a longer time before
instituting a lower release rate.
The Protocol Committee recommends
that the WCA work with AEP & the FERC during the re-licensing of the
project, so that a better protocol can be licensed for operation. To achieve this objective the committee also
encourages the WCA to participate in developing studies that need
to be accomplished during project re-licensing. Lastly, this committee
recommends that when opportunity presents it self, the release protocol should
be tested and evaluated during the period leading to relicensing. A mechanism to optimize the release
protocol, based upon conditions and experience, should be included in the new
license.
·
Drop releases to as little as 350 cfs (or alternatively, to
maintain 360 cfs @ Altavista Gage/550 cfs @ Randolph).
·
Releases should be “ratcheted” upward or downward to mimic
natural rises & falls in river elevations, and in accordance with severity
of the lake shortfall/inflows.
Spring
(February-Striper Spawn Beginning): Supercharge Above Full Pond (795.3').
· If we are in a drought of over 60 days duration, with inflows below 525 cfs, then winter discharge criteria should be followed.
·
If project is @ 794.5 or above, and inflows> 525 cfs,
then releases of 525 cfs.
·
If Smith Mountain Lake is 794.5’ at beginning, with previous
30 day inflows averaging 525 cfs, or above. If these criteria are not met,
then some semblance of striper spawn, which allows for lake level to drop no
lower than 792.8’.
Summer
(End of striper spawn through October 15): (Temperature adjustments if
necessary).
Early Summer (end of spawn-July 5)
·
If SML @ <793’ and average inflows less than 350 cfs over
previous 30 days, or lake level <792.5’ triggers release of 400 cfs with
weekend daylight Long Island river 650 cfs releases (Saturday only if lake
level is not recovering).
Mid Summer: (July 6-Labor Day)
·
Adjusted lake level below <792.5’ and 30 day average
inflows less than 400 cfs, or lake level <792’, triggers release of 400 cfs
with Saturday only river recreational releases.
Late Summer (Day after Labor Day-October 15)
·
Adjusted lake level below 792.5’ triggers release of 400 cfs
through September 15; 350 cfs for balance of period. No recreational
releases below 792’; above 792’ only as level is recovering.